Free 74-343 Training Exam Question 1

You are managing a project using Project Professional 2013. Your  project schedule is showing task over allocation indicators in the  Gantt chart view.You navigate to the Team Planner view to investigate more details regarding the over allocations. You discover  that the BA1 resource is over allocated and you  need to see all assignments with details for BA1 to understand their current workload before making any assignment changes. What should you do?

Options

A. Click the BA1 resource and scroll to the end of the project.
B. Click View, check Details, select Resource Form then click on the BA1 resource.
C. Click View, check Details, select Task Form then click on the BA1 resource.
D. Right-click the BA1 resource and select Information.

Answer: B
Show Answer

2 Exams PDF Files

$50 Original Price $ 70

  • Latest and Most Up-todate Dumps
  • Free 3 Months Updates
  • Exam Passing Guarantee
  • Secure Payment
  • Privacy Protection

3 Exams PDF Files

$70 Original Price $ 105

  • Latest and Most Up-todate Dumps
  • Free 3 Months Updates
  • Exam Passing Guarantee
  • Secure Payment
  • Privacy Protection

4 Exams PDF Files

$85 Original Price $ 140

  • Latest and Most Up-todate Dumps
  • Free 3 Months Updates
  • Exam Passing Guarantee
  • Secure Payment
  • Privacy Protection

5 Exams PDF Files

$100 Original Price $ 175

  • Latest and Most Up-todate Dumps
  • Free 3 Months Updates
  • Exam Passing Guarantee
  • Secure Payment
  • Privacy Protection